Work that has come true:
· Partial measurement on April 22
· Cleaning and clearing of the ground using a shovel 7608m²
· Excavation of topsoil 2110m³
· Excavation in the clearing area 2900m³
· Embankment with suitable material from the same excavation 1210m³
· Supply of selected material of contribution 3281.85m³
· Spreading and threshing of an artificial contribution of 1458 m³.
Machinery for the execution of the work: Caterpillar Inc. John Deere Mercedes-Benz Trucks
Excavators:
CAT 336
Motor grader:
CAT 140 H, 3D equipment
Water tank:
JOHN DEERE 8295R – 8320R
Compactors:
HAMM 3520
Dumpers:
MERCEDES 2638 6 × 6
MAN 33.410 6 × 6
MAN 41.440 8 × 6
MERCEDES AROCS 4148
#turns # construction #landwork #heavymachine #Almenar
Follow-up of the work: